Melbourne Park Redevelopment – Media & Administration Building

Melbourne Park Redevelopment – Media & Administration Building

BRD was engaged by Built for the full structure package of Melbourne Park Administration and Media Building. It is the headquarters for both Melbourne & Olympic Parks and Tennis Australia.

The building has a range of facilities such as office spaces, plant rooms, function and media overlay space. Structurally, the building was lost metal formwork on structural steel design. We were thrilled to be a part of this high-profile project with Built.

Client  

Sructural Engineer  

Site Address  

Project Value

Structure build time 

Built.

ARUP

Melbourne Park

>$30M

6 months

BRD was engaged by Built for the full structure package of Melbourne Park Administration and Media Building. It is the headquarters for both Melbourne & Olympic Parks and Tennis Australia.

The building has a range of facilities such as office spaces, plant rooms, function and media overlay space. Structurally, the building was lost metal formwork on structural steel design. We were thrilled to be a part of this high-profile project with Built.

Client  Built.

Structural Engineer   ARUP

Site Address   Melbourne Park

Project Value   >$30M

Structure build time  6 months

Nexus 3

Nexus 3

BRD was engaged by Broad/APM to complete the full structure package for a four-level building with a two-level basement car park. 8 Nexus Court houses offices for GS1 & Nestle Health Science. It is located adjacent to the Monash Freeway.

Our works involved the construction of the full structure package.  This involved the supply and placement of concrete, reinforcement and formwork to the building.

Client

Sructural Engineer

Site Address

Project Value

Structure build time

Broad/APM

4D Workshop

8 Nexus Court, Mulgrave

>$50M

6 months

BRD was engaged by Broad/APM to complete the full structure package for a four-level building with a two-level basement car park. 8 Nexus Court houses offices for GS1 & Nestle Health Science. It is located adjacent to the Monash Freeway.

Our works involved the construction of the full structure package.  This involved the supply and placement of concrete, reinforcement and formwork to the building.

Client   Broad/APM
Sructural Engineer   4D Workshop
Site Address   8 Nexus Court, Mulgrave
Project Value   >50M
Structure build time   6 months

Markethall Docklands

Markethall Docklands

BRD was engaged by Hutchinson builders to be a part of the $150m redevelopment of The District Shopping, entertainment and dining precinct. The redevelopment is called The Market and we were engaged to do the structural works in converting the ground floor and mezzanine of a 7-level car park conversion. For this project, BRD Industries used a laser screed to finish over 10,000m2 of ground floor. Our scope involved the footing strengthening, slab on ground, suspended slabs and ramps. The project was an overall success and we are grateful for the repeat business that our clients entrust us with.

Client

Structural Engineer

Site Address

Project Value

Structure Build Time

Hutchinson Builders

4D Workshop

Markethall, Docklands

>$50m

9 months

BRD was engaged by Hutchinson builders to be a part of the $150m redevelopment of The District Shopping, entertainment and dining precinct. The redevelopment is called The Market and we were engaged to do the structural works in converting the ground floor and mezzanine of a 7-level car park conversion. For this project, BRD Industries used a laser screed to finish over 10,000m2 of ground floor. Our scope involved the footing strengthening, slab on ground, suspended slabs and ramps. The project was an overall success and we are grateful for the repeat business that our clients entrust us with.
Client   Hutchinson Builders
Structural Engineer   4D Workshop
Site Address   Markethall, Docklands
Project Value   >$50m

Structure Build Time   9 months