Melbourne Park Redevelopment – Media & Administration Building

Melbourne Park Redevelopment – Media & Administration Building

BRD was engaged by Built for the full structure package of Melbourne Park Administration and Media Building. It is the headquarters for both Melbourne & Olympic Parks and Tennis Australia.

The building has a range of facilities such as office spaces, plant rooms, function and media overlay space. Structurally, the building was lost metal formwork on structural steel design. We were thrilled to be a part of this high-profile project with Built.

Client  

Sructural Engineer  

Site Address  

Project Value

Structure build time 

Built.

ARUP

Melbourne Park

>$30M

6 months

BRD was engaged by Built for the full structure package of Melbourne Park Administration and Media Building. It is the headquarters for both Melbourne & Olympic Parks and Tennis Australia.

The building has a range of facilities such as office spaces, plant rooms, function and media overlay space. Structurally, the building was lost metal formwork on structural steel design. We were thrilled to be a part of this high-profile project with Built.

Client  Built.

Structural Engineer   ARUP

Site Address   Melbourne Park

Project Value   >$30M

Structure build time  6 months

Peninsula Private Hospital

Peninsula Private Hospital

BRD was engaged by Hutchinson Builders to complete a 3000m2 car park on top of an existing structure. The project was broken up into many stages to work within a live car park environment as per the request of Ramsay Health. All in all, we managed to complete the band beam & BONDEK® structure whilst keeping the car park open with minimal disruptions to patients.

Client

Sructural Engineer

Site Address

Project Value

Structure build time

Hutchinson Builders

Taylor Thompson Whitting (TTW)

525 Mclelland Drive Frankston

>$35M

9 months

BRD was engaged by Hutchinson Builders to complete a 3000m2 car park on top of an existing structure. The project was broken up into many stages to work within a live car park environment as per the request of Ramsay Health. All in all, we managed to complete the band beam & BONDEK® structure whilst keeping the car park open with minimal disruptions to patients.

Client   Hutchinson Builders

Sructural Engineer   Taylor Thompson Whitting (TTW)

Site Address   525 Mclelland Drive Frankston

Project Value   >35M

Structure build time  9 months

Nexus 3

Nexus 3

BRD was engaged by Broad/APM to complete the full structure package for a four-level building with a two-level basement car park. 8 Nexus Court houses offices for GS1 & Nestle Health Science. It is located adjacent to the Monash Freeway.

Our works involved the construction of the full structure package.  This involved the supply and placement of concrete, reinforcement and formwork to the building.

Client

Sructural Engineer

Site Address

Project Value

Structure build time

Broad/APM

4D Workshop

8 Nexus Court, Mulgrave

>$50M

6 months

BRD was engaged by Broad/APM to complete the full structure package for a four-level building with a two-level basement car park. 8 Nexus Court houses offices for GS1 & Nestle Health Science. It is located adjacent to the Monash Freeway.

Our works involved the construction of the full structure package.  This involved the supply and placement of concrete, reinforcement and formwork to the building.

Client   Broad/APM
Sructural Engineer   4D Workshop
Site Address   8 Nexus Court, Mulgrave
Project Value   >50M
Structure build time   6 months

Melbourne Grammar School

Melbourne Grammar School

The new Geoff Handbury Science and Technology Hub at Melbourne Grammar School is a simple, singular sculptural structure. The construction of the new five-level Science and Technology Hub replaces the existing science building. The cutting edge design of this building facilitates scientific and technological investigations.

BRD Industries was engaged by Kane Construction to complete the full structure package. The project was interesting with its rounded floor plate shapes & BubbleDeck formwork system which provided some challenges during construction.

This was BRD’s 25th project with Kane Construction – a testament to our clients entrusting us with repeat business.

Client 

Sructural Engineer

Site Address

Project Value

Structure Build Time

Kane Construction

Irwin Consult

47 Domain Street, Melbourne

>$30M

6 months

The new Geoff Handbury Science and Technology Hub at Melbourne Grammar School is a simple, singular sculptural structure. The construction of the new five level Science and Technology Hub replaces the existing science building. The cutting edge design of this building facilitates scientific and technological investigations.

BRD Industries was engaged by Kane Construction to complete the full structure package. The project was interesting with its rounded floor plate shapes & BubbleDeck formwork system which provided some challenges during construction.

This was BRD’s 25th project with Kane Construction – a testament to our clients entrusting us with repeat business.

Client   Kane Construction
Sructural Engineer   Irwin Consult
Site Address   47 Domain Street, Melbourne
Project Value   >30M
Structure build time   6 months

Parliament House Office Accommodation

Parliament House Office Accommodation

Parliament House Office Accommodation is a new freestanding, two-level office building with a roof garden which was constructed to the east of the existing heritage listed Parliament House.

BRD was engaged by Cockram Construction (now ICON) to build 102 new offices, a breakout area and amenities for the Members of Parliament. This was a special project for us as not only is it a prestigious project in the heart of Melbourne, it also involved the use of BubbleDeck Formwork which is a new formwork system which saves concrete through the use of proprietary air bubbles in the slab.

BRD’s scope of work involved the structural works to the footings, ground slab, suspended slabs and the installation of BubbleDeck.

Client

Sructural Engineer

Site Address

Project Value

Structure Build Time

Icon

Irwin Consult

Spring St, East Melbourne

>$30M

7 months

Parliament House Office Accommodation is a new freestanding, two-level office building with a roof garden which was constructed to the east of the existing heritage listed Parliament House.

BRD was engaged by Cockram Construction (now ICON) to build 102 new offices, a break out area and amenities for the Members of Parliament. This was a special project for us as not only is it a prestigious project in the heart of Melbourne, it also involved the use of BubbleDeck Formwork which is a new formwork system which saves concrete through the use of proprietary air bubbles in the slab.

BRD’s scope of work involved the structural works to the footings, ground slab, suspended slabs and the installation of BubbleDeck.

Client   Icon
Sructural Engineer   Irwin Consult
Site Address   Spring St, East Melbourne
Project Value   >30M
Structure build time   7 months

Maroondah Hospital Car Park

Maroondah Hospital Car Park

BRD was engaged by Hutchinson Builders to construct a 542 space multi-deck car park which was officially opened on Monday 28th of October 2019. The multi-deck car park will increase capacity across the hospital precinct. The new carpark which is affectionally known as Grey Street car park is a staff-only car park which will improve the availability of existing parking spaces to patients. The structure consisted of a Bondek on structural steel. BRD was engaged to supply and place concrete, reinforcement & lost metal formwork. It was a successful project and one we are thrilled to be a part of.

Client

Site Address

Project Value

Structure Build Time

Hutchinson Builders

Lot 8-16 Grey Street, Ringwood

>$12M

4 months

BRD was engaged by Hutchinson Builders to construct a 542 space multi-deck car park which was officially opened on Monday 28th of October 2019. The multi-deck car park will increase capacity across the hospital precinct. The new carpark which is affectionally known as Grey Street car park is a staff-only car park which will improve the availability of existing parking spaces to patients. The structure consisted of a Bondek on structural steel. BRD was engaged to supply and place concrete, reinforcement and lost metal formwork. It was a successful project and one we are thrilled to be a part of.
Client   Hutchinson Builders
Site Address   Lot 8-16 Grey Street, Ringwood

Project Value   >$12M

Structure Build Time   4 months

Fishermans Bend Secondary School

Fishermans Bend Secondary School

BRD was engaged by Hutchinson Builders to be the main structure contractor for Fishermans Bend Secondary School (FBBS). FBBS is funded through the 100 New Schools Victorian Government Initiative. It involves the construction of the state-of-the-art school building at 477 Graham Street, Port Melbourne in the Mirraway Precinct. FBBS is a science, technology, engineering, arts and maths (STEAM) focused school.  The building has some fantastic amenities such as:

  • Fabrication Lab
  • Robotics Workshop
  • 200-seat lecture theatre
  • Gymnasium with competition grade basketball and netball facilities
  • Food technology area with commercial-grade kitchen and canteen
  • Performing arts amenities
  • Outdoor Terraces
  • Urban garden with recreational ball sports areas
  • Kitchen Garden
As the main structure contractor for Hutchinsons Builders, BRD was involved in completing the structure works to the footings, slab on ground and suspended slabs. This was also the first project where we did our own formwork.

Client

Site Address

Project Value 

Structure Build Time

Hutchinson Builders

477 Graham Street, Port Melbourne

>$35M

6 months

BRD was engaged by Hutchinson Builders to be the main structure contractor for Fishermans Bend Secondary School (FBBS). FBBS is funded through the 100 New Schools Victorian Government Initiative. It involves the construction of the state-of-the-art school building at 477 Graham Street, Port Melbourne in the Mirraway Precinct. FBBS is a science, technology, engineering, arts and maths (STEAM) focused school.  The building has some fantastic amenities such as:

  • Fabrication Lab
  • Robotics Workshop
  • 200-seat lecture theatre
  • Gymnasium with competition grade basketball and netball facilities
  • Food technology area with commercial-grade kitchen and canteen
  • Performing arts amenities
  • Outdoor Terraces
  • Urban garden with recreational ball sports areas
  • Kitchen Garden
As the main structure contractor for Hutchinsons Builders, BRD was involved in completing the structure works to the footings, slab on ground and suspended slabs. This was also the first project where we did our own formwork.
Client   Hutchinson Builders
Site Address   477 Graham Street, Port Melbourne

Project Value   >$35M

Structure Build Time   6 months

Markethall Docklands

Markethall Docklands

BRD was engaged by Hutchinson builders to be a part of the $150m redevelopment of The District Shopping, entertainment and dining precinct. The redevelopment is called The Market and we were engaged to do the structural works in converting the ground floor and mezzanine of a 7-level car park conversion. For this project, BRD Industries used a laser screed to finish over 10,000m2 of ground floor. Our scope involved the footing strengthening, slab on ground, suspended slabs and ramps. The project was an overall success and we are grateful for the repeat business that our clients entrust us with.

Client

Structural Engineer

Site Address

Project Value

Structure Build Time

Hutchinson Builders

4D Workshop

Markethall, Docklands

>$50m

9 months

BRD was engaged by Hutchinson builders to be a part of the $150m redevelopment of The District Shopping, entertainment and dining precinct. The redevelopment is called The Market and we were engaged to do the structural works in converting the ground floor and mezzanine of a 7-level car park conversion. For this project, BRD Industries used a laser screed to finish over 10,000m2 of ground floor. Our scope involved the footing strengthening, slab on ground, suspended slabs and ramps. The project was an overall success and we are grateful for the repeat business that our clients entrust us with.
Client   Hutchinson Builders
Structural Engineer   4D Workshop
Site Address   Markethall, Docklands
Project Value   >$50m

Structure Build Time   9 months